Sioux Falls Ford

Thanks for the report. A bit hard to tell from the picture, but it looks like it may be set up for at least 2 stalls, maybe 3, or even as many as 6 if the pedestals are dual connector. Any more information there?

The permit states 28 EV chargers, and while most of those are probably L2, that's still quite an impressive number!
 
Swung back through here this weekend. The transformer hasn't been set, nor any chargers. Taking a closer look at the conduits, it looks like 2 DCFC and one AC pedestal will go out by the picnic area straight out from the maintenance entrance. Then there's a separate line for multiple AC pedestals along the entrance row of vehicles. Will be interesting to see how that row works as it's parked full of new vehicles currently.
 
New pictures on plugshare show 2 likely 180kW EV Connect chargers with dual CCS cords and 3 likely 24kW CCS chargers along the entrance row! No new pictures from the picnic table area.
 
Looks like the electrical service inspection was passed on 12/27/2023, hopefully these will progress quickly from there.
 
Transformer has been installed and the 24kW units are powered up but not added onto the EV Connect network. 180kW units haven't been powered up yet.
 
Back