Electrify America @ Broken Arrow, OK

Mockingbird

Active member
Fastcharger Editor
Joined
Jan 30, 2022
Messages
470
Target T2422 (Broken Arrow, OK)

1150 E Hillside Drive, Broken Arrow, Oklahoma 74012-2385

Electrify America network
 
An anonymous user submitted a change proposal to move this site to construction. I don't see any evidence of this on Plugshare (nor here in the forum). Is there any supporting evidence for this?
 
An anonymous user submitted a change proposal to move this site to construction. I don't see any evidence of this on Plugshare (nor here in the forum). Is there any supporting evidence for this?
I don't suppose there are too many local users in OK who could check on this.
 
An anonymous user submitted a change proposal to move this site to construction. I don't see any evidence of this on Plugshare (nor here in the forum). Is there any supporting evidence for this?
I posted that as I saw on the Broken Arrow Buzz (BA Buzz) Facebook page posted the following picture and update on 10/15/2023:FB_IMG_1697855072608.jpg
 

Attachments

  • Screenshot_20231021_201424_Facebook.jpg
    Screenshot_20231021_201424_Facebook.jpg
    197.9 KB · Views: 2
I stopped by this location today and spoke to the EA site manager. They are beginning to set equipment today and plan to wrap up this week. After that it will be the meter installation by PSO and inspections by the City of Broken Arrow. Electrify America is hoping to have the site commissioned by November 15th, 2023.
 

Attachments

  • 20231030_122113.jpg
    20231030_122113.jpg
    302.4 KB · Views: 5
I stopped by this location today and spoke to the EA site manager. They are beginning to set equipment today and plan to wrap up this week. After that it will be the meter installation by PSO and inspections by the City of Broken Arrow. Electrify America is hoping to have the site commissioned by November 15th, 2023.
Excellent.

Keep us posted.
 
Transformer, switch gear, meter, and inspection are all complete - looks like EA could kick it on at any time. Meter shows 0 kwh delivered. Still missing the light though, lol.
 

Attachments

  • 20231129_143808.jpg
    20231129_143808.jpg
    248.1 KB · Views: 4
  • 20231129_143746.jpg
    20231129_143746.jpg
    246.1 KB · Views: 4
  • 20231129_143733.jpg
    20231129_143733.jpg
    255.9 KB · Views: 4
Not open yet, but it was added to AFDC today, so expect it to happen in the next 2-4 weeks.
 